Sana'a: The Deputy Governor of Sana'a for Technical Affairs, Engineer Saleh Al-Muntasir, inspected the progress of the Gaza Street rehabilitation project. This project, which extends from 50th Street to Al-Ra'ad Roundabout in the New Sana'a District, is being carried out by the Sana'a Governorate's Maintenance and Restoration Executive Unit, under the supervision of the Governorate's Public Works Office.
According to Yemen News Agency, Deputy Governor Al-Muntasir reviewed the reinforced concrete work for the surface bridges in the first phase of the project. These bridges, with a height of 15 cm, extend from station (0+400) to station (0+840). The first phase involves the use of 200 cubic meters of concrete and covers a total area of 1,400 square meters, with an estimated cost of 70 million riyals.