Sana’a Water Corporation Completes Emergency Sewer Line Replacement on Marib Street

Sana'a:The Local Corporation for Water and Sanitation in the Capital Sana'a has successfully completed emergency operations to replace the collapsed main sewage line on Marib Street in the Shu’ub district.

According to Yemen News Agency, the corporation's Director, Engineer Mohammed Mada’es, announced that maintenance teams finalized the replacement work on Friday evening. The project involved installing a new 72-meter-long, 800-mm-diameter main sewer line after the previous line failed due to its age.

The three-day project, funded by the corporation, included replacing the damaged asbestos pipes with new glass-reinforced plastic (GRP) pipes. The work also encompassed excavation, backfilling, street rehabilitation, and debris removal. Mada’es confirmed that technical teams would continue maintenance and cleaning activities on sewage networks throughout the various districts of the Capital Sana'a.